Final stages of construction have begun!

By April 8, 2021May 13th, 2021No Comments

April 8, 2021

Latest update:

  • Office interiors being completed – paint, tile, ceilings, fixtures, etc.
  • Warehouse finishing up lighting, fire suppression, dock and rail doors, dock office, IT closet.
  • Starting exterior work – concrete for parking, driveways, truck docks, entrance roads.
  • Finishing up roof work – edge cap, down spouts, roof air units.
  • Weather permitting, will begin landscaping soon, weather permitting.
  • Work has begun on rail culvert and final grading.