December 4, 2020

Construction continues at Logistics Park Cedar Rapids. The office is now fully enclosed and the framing and sheet rock have been moving ahead.

All the wall panels are on-site and expected to be up by next week.

We’re installing gas lines and plan to have heat on in the facility by the end of December 2020.